DEL-06-03

Project Management Workspace

Integrated task management, CAD drawing revisions, and calculation notebook tracking (Session Runtime State).

MLS-SUB-01

Substructure & Framing IFC Submission

33% Complete
TSK-STR-001
HIGH

Design Main Beam B101 Reinforcement

Calculate design moment, check minimum depth against span ratio, and update CAD drawing.

CAD Drawing Links
REV-ABEAM_B101
MODIFICATION
2 calculation cells
TSK-STR-002
CRITICAL

Column C1 Grid Verification

Verify axial capacity under tributary dead and live loads.

CAD Drawing Links

No drawings linked

TSK-STR-003
MEDIUM

Substructure Foundation Footing F1-F4

Finalize isolated footing dimensions and soil bearing capacity check.

CAD Drawing Links
REV-0FOOTING_F1, FOOTING_F2, FOOTING_F3, FOOTING_F4
ADDITION